This is an AAO appeal decision — a case denied once and appealed. It shows how the framework is applied; it is not the filing population.
The Petitioner sought to continue working as an operations manager overseeing computerized cutting and fabrication of metal building components for his current construction employer.
Field: computerized metal cutting and fabrication / construction · Read the decision (uscis.gov)
EB-2 threshold — not met
AAO found the Petitioner did not qualify as an advanced degree professional (foreign credential equated only to a U.S. associate's degree, and experience cannot substitute for a bachelor's degree) nor as an individual of exceptional ability (met only 2 of 6 regulatory criteria: education and 10 years' experience; failed certification, salary, membership, and recognition criteria).
Prong 1 — national importancenot established · dispositive
“the Petitioner has not shown how his proposed work for his employer will potentially have broader implications for the industry or substantial positive economic effects for the region or nation”
“the focus of the Dhanasar framework's first prong is the petitioner's specific endeavor, not the entire industry or field in which they work”
“these expert opinion letters do not support the national importance of the Petitioner's proposed endeavor”
“these reports show the national importance of the construction industry as a whole, and therefore do not support the importance of the Petitioner's specific proposed endeavor”
AAO decision text
How the evidence was treated
- degree · discounted
“the Petitioner has not established that his degree is equivalent to a U.S. bachelor's degree”
AAO decision text - resume experience · credited
- certification membership · discounted
“does not show that this certification is required for entry into the Petitioner's occupation or is specifically tailored for that occupation”
AAO decision text - recommendation letter · discounted
“these letters were prepared for purposes of this petition”
AAO decision text - other · discounted
“even if the Petitioner had submitted sufficient evidence of his salary, this evidence is not a sufficient basis for comparison”
AAO decision text
All 6 evidence items
- media · discounted
“these reports show the national importance of the construction industry as a whole, and therefore do not support the importance of the Petitioner's specific proposed endeavor”
AAO decision text
Where this case turned
- Employer-specific benefit · p1 — "work furthers my company's product" — value accrues to one firm
- Field importance conflated with endeavor · p1 — argues the field matters, not the specific endeavor
- Letters conclusory · p1 — letters praise skills in general terms without tracing specific impact
- Local, not national scope · p1 — impact confined to clients / a region
Notable
AAO withdrew the Director's implicit finding of advanced-degree eligibility and conducted a full independent threshold EB-2 analysis (both advanced degree and exceptional ability tracks) because the Director's decision was unclear on this point. AAO also reached and analyzed Dhanasar prong 1 despite the threshold failure being independently sufficient, then declined prongs 2 and 3.
Authorities this decision leans on
From the doctrinal survivor set — 187 authority tests across 47 distinct authorities cleared the differential-lift gates. Only those appear here.
- 8 C.F.R. 103.3
- 8 C.F.R. 204.5(k)(2)
- 8 C.F.R. 204.5(k)(3)(ii)
- 8 C.F.R. 204.5(k)(3)(iii)
- Poursina v. USCIS
Cases in adjacent profiles
- The Petitioner, a mechanical engineer, proposed to advance thermal management solutions for high-power, compact, and rel
- The Petitioner, a senior engineering program manager specializing in electromechanical systems, proposed to advance moto
- The Petitioner proposed to provide innovative solutions to optimize freight and vessel operations in the U.S. shipping i
- The Petitioner, a sales manager, proposed an endeavor in the United States for which he sought an EB-2 national interest
- The Petitioner proposed to lead a nationwide initiative to develop and implement a standardized materials management mod